Project status

July 17, 2014

Click here to view the PDF of the PowerPoint presentation used July 15 to update the City Council regarding Iowa City Gateway plans. The landscaping and corridor aesthetic photos shown are potential concepts only.  More information will be provided as we continue final design.

July 11, 2014

Click here to see the July 10 City Council Packet information regarding the Iowa City Gateway project. The public is invited to attend the July 15, 2014 City Council work session, where the Iowa City Gateway design team will discuss plan updates and seek input on landscaping and corridor aesthetic concepts.  The meeting will begin at 5 p.m.

April 11, 2014

Click here to see the April 9 Council Packet information for the Iowa City Gateway Project.

April 4, 2014

Click here to see the Design Element Spreadsheet as passed by the City Council on April 1, 2014.

The design team will now move into the preliminary design phase, using these elements to guide the project.

Click on each rendeering below to see it full size.

View from Boat House View of Dubuque Street and Foster looking south View of Dubuque Street at Kimball looking south View of Dubuque Street at Taft looking south View of Dubuque Street from City Park View of Dubuque Street from Mayflower Hall View of Park Road looking east

March 27, 2014

Click here to see the March 27 City Council packet.

March 26, 2014

Click below to see information shared at the March 25 City Council meeting:

Council Presentation – Click here

Traffic Memo – Click here

March 21, 2014

Click below to see the contents of the March 20, 2014 City Council Packet:

Gateway Project Design Elements Memo – Click here

Arterial Street Lane Width Comparison – Click here

Pre Design Public Meeting Summary – Click here

Conceptual Project Renderings – Click here

Conceptual Project Cross Sections – Click here

Conceptual Project Typical Sections – Click here

Conceptual Project Park Road Bridge Elevations – Click here

February 26, 2014

Pre-Design Meeting: The Conceptual Design for improvements to Dubuque Street and replacement of the Park Road Bridge has been revised, based on design parameters established by the City Council in January, 2014.

Thanks to the nearly 100 citizens who participated in the Drop-In Center on February 25th.

The conceptual design shows the new, reduced footprint of the project, based on council direction from January, 2014.

PDM Roll Plot

(click to enlarge)

Click here to see the exhibits from the Drop-In Center

Click here to see the presentation made at the Drop-In Center

Please let us know what you think.  With your input, the design team will then prepare to discuss specific design elements for the project with the City Council at the March 25, 2014 work session.

To print out a comment form click here.  (You do NOT need to complete a form if you would prefer to submit your comments in letter or other format).  To access an interactive PDF form, click here. You may also e-mail your comments by clicking here.

The Conceptual and Preliminary design process is expected to take 4 months, with the Final Design process expected to take 8-12 months. Immediately following the design phase, the City will begin the letting process for construction. The project schedule can be viewed here.

If you would like to be notified of public meetings and to receive project updates, or if you have additional comments or questions, click here.

January 23, 2014

On January 21, 2014, the City Council discussed the project during the informal work session and approved design parameters for the Iowa City Gateway Project at the formal meeting. Those primary design parameters for the project are: Protection level for Dubuque Street will be the 100-year flood elevation plus one foot, Backwater Reduction Goal (low steel elevation) for the Park Road Bridge will be the 200-year flood elevation plus one foot and the structural type for the bridge will be a Through Arch.

To see renderings of the selected alternatives, click here.

To see the presentation made to the City Council, click here.

To see a summary of the discussion and decisions from the City Council work session and formal meeting, click here.

January 17, 2014

The public is invited to attend the January 21, 2014 City Council meeting.  A brief presentation will be made at the 5 p.m. work session, followed by City Council questions and project discussion.  A resolution has been placed on the Agenda for the 7 p.m. City Council Meeting.  The City Council is being asked to establish the following three design parameters:  (1) the level of protection for Dubuque Street, (2) the backwater reduction goal (elevation of the Park Road Bridge), and (3) the structural type of the bridge.  City staff has recommended that the design parameters be:  (1) protect Dubuque Street to the 2008 flood elevation plus one foot and, (2) provide backwater reduction by elevating the low steel of the new bridge to the 200-year flood plus one foot and, (3) proceed with either the Through Arch Bridge or the Deck Girder Bridge.  The public will be able to comment during the discussion of the Agenda item.

To see a copy of the City Council Packet, click here.

To see a copy of the presentation made to the City Council, click here.

December 19, 2013

The City of Iowa City has received notification from the Iowa Department of Transportation that the Federal Highway Administration (FHWA) has approved and signed the Finding of No Significant Impact (FONSI) for the Iowa City Gateway Project. The approval was dated December 18, 2013. The FONSI is the final step in the National Environmental Policy Act (NEPA) process. The project is now cleared to move forward in the design process. Click here to view the FONSI document.

Design parameters for the Gateway Project will be discussed by the City Council on January 21, 2014. Additional details will follow.

November, 2013 Update

At the request of the Iowa Department of Transportation (DOT), the Finding of No Significant Impact (FONSI) document has been submitted for review. The Iowa DOT will review the document and then submit it to the Federal Highway Administration (FHWA) for final review and approval. Federal approval of the FONSI represents the final step in the National Environmental Policy Act (NEPA) process.

At this time, Iowa City has not been made aware of a final resolution to the Section 106 process requests made by the Advisory Council on Historic Preservation (ACHP) to the FHWA.

City Council Review

The Iowa City Council is in the process of reviewing the project to establish parameters for design.  At a work session on September 17, 2013 the Council heard a presentation from city staff and the design consultant.  An overview of the Environmental Assessment/NEPA process and the Preferred Alternative was given before moving on to discuss the Design Decisions that will need to be made by the City Council prior to final design and engineering.  These decisions include: the level of protection for Dubuque Street, backwater reduction goals and structural type of the bridge.

A range of options was provided and, based on preliminary design information, cost estimates, roadway elevations and water surface elevations were provided.  The “Do Nothing” option was addressed as well, which includes many needed improvements to the aging infrastructure in the corridor.

A copy of the presentation made to the City Council on September 17 can be found here, and City Council packet contents can be found here.

The City Council continued to review the Iowa City Gateway project at their October 1, 2013 work session.  That same night, there was an agenda item for public input on the project at the 7 p.m. formal Council meeting.  Staff outlined recommendations in a presentation and then opened the floor for public comment.  Additionally, staff made note of questions from the public and will follow up with discussion and responses in a future council information packet/session.

A copy of the presentation made to the City Council on October 1 can be found here, and City Council packet contents can be found here.

Environmental Assessment Review Status

The Federal Highway Administration has indicated that their process for responding to the Advisory Council on Historic Preservation will not be complete prior to the October 1st City Council meeting.  Formal council action regarding design parameters will not occur until after the NEPA process is complete.

The Iowa City Gateway Environmental Assessment

The City of Iowa City has studied potential solutions to minimize flood impacts on Dubuque Street and Park Road, reduce backwater created by Park Road Bridge and make needed infrastructure improvements in the corridor.

Recommendations for those improvements, as well as potential adverse and beneficial impacts to the community, buildings and the natural environment are detailed in the Iowa City Gateway Environmental Assessment (EA).

See draft renderings of the final project

See maps of the recommendations  

See the Environmental Assessment document

See the public meeting transcript

See comments submitted during the official comment period

What is the Iowa City Gateway Project?

The Iowa City Gateway project will design and build solutions for the flooding that affects the Dubuque Street/Park Road Bridge Corridor. The goal is to ensure the Dubuque Street and the Park Road Bridge can remain open even during a 500-year flood event.

As part of this project, the City of Iowa City has developed and evaluated various alternatives for improving Dubuque Street and replacing Park Road Bridge. Once the recommended alternative receives Federal approval, more detailed design and engineering plans will be developed, followed by construction of the new road and bridge.

Read more about the project’s Phase 1 plan

Project News & Events

Spring 2013 – The official comment period on the Environmental Assessment was March 14 – April 15, 2013.  Public comments received via letter, e-mail or verbally at the public hearing during that period have been included in the document which has been submitted for final, Federal review and approval.

As a part of that comment period, a public drop in center and a public hearing were held on April 4, 2013.  At the meeting, the roughly 45 attendees had an opportunity to learn about the project process and provide input regarding the EA document, the preferred alternative, and corridor needs.  The attendees could also ask questions of the design team and City staff, see a short presentation about the project and provide formal comments about the recommendations in the Environmental Assessment.

See more about the public hearing.

August 2012 *UPDATE* – Project documents are currently being reviewed by local, state and federal agencies.  Once those reviews are complete the City of Iowa City will provide information on public review and comment opportunities, including the date, time and location of a public meeting.

December 8, 2011 – Draft Alternatives Available for Public Review – Because the community has shown so much interest in the project, Iowa City added an opportunity for the public you to see preliminary, draft versions of the alternatives being developed at a drop in center hosted on December 8, 2011.

March 3, 2011 – The first Iowa City Gateway public meeting was held from 4:30 to 7 p.m., Thursday, March 3, 2011, at the Parkview Church, 15 Foster Road, and is located just adjacent to the project study area in Iowa City.  At the meeting, more than 150 attendees had an opportunity to learn about the project process, provide input regarding corridor needs, ask questions, sign up to receive project information, and see a short presentation about the project and its current status.

July 13, 2012 – The second Iowa City Gateway public meeting was held from 4:30 to 7 p.m., July 17, 2011.  Along with an open house component, a formal presentation was made which was followed by a question and answer session.  The meeting was held at the Parkview Church, 15 Foster Road, and is located just adjacent to the project study area in Iowa City.  At the meeting, nearly 100 attendees had an opportunity to learn about the project process, provide input regarding corridor needs, ask questions, sign up to receive project information, and see a short presentation about the project and its current status.

Where Are We in the Project?

The Iowa City Gateway Project currently is nearing the end of Phase 1.  In Phase 1, the City of Iowa City will complete a federally required environmental study. The study documents the National Environmental Policy Act decision-making process that federal regulations and standards require for the Iowa City Gateway Project to access federal funds. Within the process, the team has evaluated how various design alternatives may affect the Iowa River, its floodplain and nearby neighborhoods, properties and community resources.

Phase 1 is expected to be completed in mid 2013. (Required reviews extended the original schedule.)  Phase 1 resulted in a recommended approach for improvements.

Following final, Federal approval, Phase 2 will produce detailed design and engineering of the Dubuque Street and Park Road Bridge improvements will begin. It is expected to take approximately 18 to 20 months.

Construction is anticipated to begin at the conclusion of Phase 2 and will take approximately two construction seasons to finish.

Review the Phase 1 Plan

Partners for a Successful Iowa City Gateway

The Iowa City Gateway Project is a partnership led by the City of Iowa City in cooperation with the Iowa Department of Transportation, the Federal Highway Administration and U.S. Economic Development Administration. Together, these agencies and the City’s engineering consultant form the study team that will be responsible for making the Iowa City Gateway Project a success.